Scope of Construction and Exclusion

BEYOND TECHNOLOGY · HANJIN ELEVATOR

PRODUCTS

Scope of Construction and Exclusion

The following are construction and electric works that are not included in our installation projects.

 

Division Description Construction Electricity
Hoist way Poring of each floor entrance areas (entry, elevation button, location displayer, hall lantern, etc.) and finishing of walls after installation (filling with mortar)
Fixing steel applied to the right and the left doors of the entry
Installation of ladders and electrical outlets for inspection of pit
Finishing construction after water-proof processing inside pit and mounting of a buffer
Supply and installation of hoist way barriers and intermediate materials (if necessary)
Removal of various pins and molds
Installation of safe banister on each floor entry to prevent falls
Wiring of electrical outlets
Piping and wiring of electric cords when installing CCTVs
Slope of hoist way shall be 0~30mm
Others (presented in a drawing)
Machine Room Take-in way on the floor, poring, others in a drawing and finishing (cinder concrete)
Installation of pulley beams and hooks on the ceiling
Installation of supplementary materials on the floor (if necessary)
Free supply of water for construction during installation
Free supply of a construction office and a place to store devices and materials
Installation of the entrance door before commencement of installation of elevators
Piping, wiring and finishing outside the hoist way when installing interphones in places other than machine rooms
Installation of lighting facilities and inspection light outlets
Power construction and free power supply for construction and test operation during installation
Wiring and piping for electricity for monitoring when applying monitoring boxes (monitoring box ~ hoist way)
Inlet and incoming panel construction up to each main incoming panel of emergency electricity as well as power and lighting inside a cage
Matters of Attention Related to Construction The machine room entry is a fire door. It shall not be a passage to another place.
Avoid exposed alignment of ducts, pipes, electricity, water, gas and fire hydrant for other purposes on the interior of the machine room and the hoist way and walls
The bottom of the pit cannot be used for housing, passaging and other purposes of humans
Power and voltage change ranges shall be -10%~+5%.
Install ventilation windows, ventilators and other air conditioners so that the machine room temperature and humidity do not exceed 40℃ and 90%, respectively. Also be careful not to cause noxious gases and dust.